HONKISAAREN-
NEVA SOLAR PARK
PROJECT DESCRIPTION
Project overview:
-
Site area: 50 hectares
-
Installed capacity: 34 MWp
-
Substation capacity: 31.5 MVA
-
Construction started: November 2024
-
Commissioning deadline: February 2026
-
Supported by RENEWFM program
Solarigo is constructing an industrial-scale solar park on a former peat production area of Kuortane's Honkisaarenneva. The park's annual production estimate is at maximum 31 GWh. The production corresponds to the electricity consumption of more than 1,500 electrically heated houses. The EU has supported Honkisaarenneva solar park project. The views and writings expressed on this page only reflect the view of Solarigo Systems Oy, and do not reflect the views of the European Union or CINEA (European Climate, Infrastructure and Environment Executive Agency), which granted the support, and the aforementioned entities cannot be held responsible for the contents of this site.
PANELS
65,000
INVESTMENT M€
~ 25.5
PHASE
CONSTRUCTION
LOCATION
KUORTANE
CAPACITY
34
Add a Title
Lorem ipsum
Add a Title
Lorem ipsum
PROJECT PROGRESS

Development
The project started in cooperation with the landowners of Honkisaarenneva.
After Solarigo Systems Oy's initial examination, the project was perceived as having potential. Investment support for Large Demonstration Projects of New Energy Technology was applied for the project from EU through Ministry of Economic Affairs and Employment.
05 / 2022
05 / 2022

Construction permit
Kuortane Honkisaarenneva solar park received a construction permit in March 2023.
03 / 2023
03 / 2023

The EU supports the project
The European Union supports the project through the EU's RENEWFM mechanism with 4,131,273 euros.
04 / 2024
04 / 2024

11 / 2024
Construction begins
Solarigo Systems Oy kicks out the construction of Honkisaarenneva Solarpark.
11 / 2024
_edited.png)
11 / 2024
Installations begins
The installation of mounting systems and solar panels at the Honkisaarenneva Solar Park began in February 2025. Tree removal and water protection structures were completed during the winter. Earthworks continue simultaneously with the installations.
02 / 2025

Foundation work nearing completion
The site's piling is in its final stages, and access road construction is underway. Approximately 40% of the mounting systems and panel installations have been completed.
11 / 2024
05 / 2025