CALLIO

PROJECT DESCRIPTION

Solarigo Systems Oy was responsible for the implementation of the Pyhäjärvi Callio solar park, with a capacity of 13 MWp.

The solar park built in Callio was part of the overall Callio-Hitura project, of which the Hitura project is still in the feasibility stage. The project, formerly known as Callio-Hitura, which initially explored the construction of a 75 MW solar park, has since been divided into separate Callio and Hitura projects.

The aim of the project is to develop a concept for repurposing decommissioned mining areas for renewable solar power production in the Nordic countries. In addition, a total of 7.5 MW of electricity storage capacity will be built in connection with the parks.

 

The Ministry of Economic Affairs and Employment has granted the project Next Generation EU funding for its implementation.

The project is being carried out in cooperation with Skarta Energy and Lumme Energia. For the purposes of the project, a project company named Callio-Hitura Solarpark has been established.

STEP

PRODUCTION

LOCATION

PYHÄJÄRVI

13

CAPACITY

PANELS

22 800

DJI_20250604095311_0004_V (1) (1)-min.JPG

Production started

The Callio solar park was commissioned in June 2025.

9 / 2024

6 / 2025

Add a Title

Lorem ipsum

Add a Title

Lorem ipsum

PROGRESS OF THE PROJECT

Development

The project began to be prepared in cooperation with the city of Pyhäjärvi, Pyhäsalmi Mine Oy and the Callio Energy Park project in Pyhäjärvi.

The mine tailings lands, which have gone out of use, were identified as the project area. Tailings lands cannot be used for anything other than lightweight structures, for example solar power plants.

01 / 2021

01 / 2021

Design

The exact technical planning of the Callio solar park began in April 2022. In addition, the preparation and approval of the permit processes started.

04 / 2022

04 / 2022

NextGeneration EU

The Ministry of Economic Affairs and Employment supported the project with Next Generations EU support according to the EU's recovery and reciliency plan for the project company Callio-Hitura Solarpark Oy.

12 / 2022

12 / 2022

Building permit for Callio

Callio, more specifically Callio Energy Park I received a building permit in December 2023. In the picture, an illustrative picture of the solar park.

12 / 2023

12 / 2023

DJI_0150.jpg

Callio's construction

The construction of the foundations of Callio solar power plant began in April 2024 and the panel installation in June 2024.

Solarigo Systems Oy is responsible for the construction of Callio solar power plant.

4 / 2024

4 / 2024

Construction of the expansion section

The construction of the expansion part of Atria Auringo started with earthworks after the soil had been sealed enough in May 2022. Solar panel installation started in August 2022.

05 / 2022

2019

Implementation of the plugin

The 5.0 Megawatt expansion part of Atrian Auring was put into operation in March 2023. As a new technology, double-sided bi-facial solar panels were used in the park.

The extension part was built as a single park complex on the east side of the factory area.

With the expansion, Atria covers approximately 8% of its electricity consumption with emission-free solar electricity.

03 / 2023

2019

DJI_20240918120544_0309_D.jpg

Panel installations complete in Callio

The solar panel installations were completed on schedule six months after the construction of the PV plant began.

9 / 2024

9 / 2024

MORE INFORMATION

JUHO
LASONEN

Senior Project Manager